LNG project

Rating: 1.0 of 5. 1 vote(s).

two managers's conflict about how to finish the project

D: complete the footings for gas turbines by 1st November
D': complete the footings for the gas turbines by 30th November
B: pay 1.5 mil more to pushing up the equipment to complete the footings
C: keep running project in the original schedule
A: complete the footings for turbines by 30th November as in contract
Click on the icons on the arrows to see assumptions and injections
In order to complete the footings for turbines by 30th November as in contract I must pay 1.5 mil more to pushing up the equipment to complete the footings and in order to pay 1.5 mil more to pushing up the equipment to complete the footings I must complete the footings for gas turbines by 1st November. But, in order to complete the footings for turbines by 30th November as in contract I must also keep running project in the original schedule and in order to keep running project in the original schedule I must complete the footings for the gas turbines by 30th November. I can't both complete the footings for gas turbines by 1st November and complete the footings for the gas turbines by 30th November.
RelationAssumption(s)Injection(s)