The sequence of orders

The sequence of orders

B: Have enough capacity at the cutter
D: Get the orders painted in sequence of batch numbers
A: Deliver orders to customers as promised
B-D:Assumption(s)Injection(s)
1. The workorders I receive from planning are grouped by batchnumbers.
C: Focus on the delivery weeks of the orders
D': Get the orders painted in sequence of delivery week

In order to Deliver orders to customers as promised I must Have enough capacity at the cutter and in order to Have enough capacity at the cutter I must Get the orders painted in sequence of batch numbers. But, in order to Deliver orders to customers as promised I must also Focus on the delivery weeks of the orders and in order to Focus on the delivery weeks of the orders I must Get the orders painted in sequence of delivery week. I can't both Get the orders painted in sequence of batch numbers and Get the orders painted in sequence of delivery week.

RelationAssumption(s)Injection(s)
B-D1. The workorders I receive from planning are grouped by batchnumbers.
A-C1. A preceeding batch can contain orders with sooner delivery than the batch it is preceeding.